Capacity
50.4 MW
Grid ID ast_1af5b22f3c749ea5
What is Frodsham Marsh, and what is its status?
Onshore wind in North Wales, Merseyside and Cheshire. Details below come from the sources listed for each field.
50.4 MW
Counted REPD megawatts
Published, approximate
Contains public sector information licensed under the Open Government Licence v3.0.
Contains public sector information licensed under the Open Government Licence v3.0.
REPD reference
3694
Frodsham Marsh in REPD.
DUKES site
WON-001150
Frodsham Wind Farm in DUKES.
Same site
name
Same site in both registers, matched by name (high). REPD megawatts count. Distance 1970 m.
Operator · REPD
Foresight/Belltown
REPD records 3694 as the operator.
Operator · DUKES
RES Group
DUKES records WON-001150 as the operator.
Owner · DUKES, REPD
—
The register records an operator, not an owner.
Frodsham Marsh
REPD · 3694 · Foresight/Belltown · North West · Cheshire
Frodsham Wind Farm
DUKES · WON-001150 · RES Group · North West
May 2026
30 Jul 2026 · DUKES · 50.4 MW · Not counted
REPD Q2 2026
3 Aug 2026 · REPD · 50.4 MW · Counted
DUKES
May 2026
REPD
REPD Q2 2026