What is Cuileig Hydro Scheme, and what is its status?

Hydro in North Scotland. Details below come from the sources listed for each field.

Capacity

3.3 MW

Capacity basis

Counted REPD megawatts

Location precision

Published, approximate

Location

Published, approximate
100 km

57.76327, -5.03923

Open in Map

Contains public sector information licensed under the Open Government Licence v3.0.

Contains public sector information licensed under the Open Government Licence v3.0.

Identity and relationships

  • DUKES site

    HNF-000227

    River Cuileig in DUKES.

  • REPD reference

    434

    Cuileig Hydro Scheme in REPD.

  • Same site

    coordinates

    Same site in both registers, matched by coordinates (high). REPD megawatts count. Distance 0 m.

Output

Grid does not have this data yet. It will appear here once Elexon BMU metering is added.

Ownership and operator

  • Operator · DUKES

    SSE Group

    DUKES records HNF-000227 as the operator.

  • Operator · REPD

    Scottish Hydro-Electric plc

    REPD records 434 as the operator.

  • Owner · DUKES, REPD

    —

    The register records an operator, not an owner.

Related projects

  • River Cuileig

    DUKES · HNF-000227 · SSE Group · Scotland

  • Cuileig Hydro Scheme

    REPD · 434 · Scottish Hydro-Electric plc · Scotland · Highland

Change history

  • May 2026

    30 Jul 2026 · DUKES · 3.3 MW · Not counted

  • REPD Q2 2026

    3 Aug 2026 · REPD · 3.3 MW · Counted