Grove Solar Park (Phase 1): 5 MW Solar PV | Grid

Grove Solar Park (Phase 1)

Solar PVOperational

Grid ID ast_5257822d3721b5df

View on map

What is Grove Solar Park (Phase 1), and what is its status?

Solar PV in Southern England. Details below come from the sources listed for each field.

Capacity

5.0 MW

Capacity basis

Counted REPD megawatts

Location precision

Published, approximate

Location

Published, approximate
100 km

50.96362, -1.47899

Open in Map

Contains public sector information licensed under the Open Government Licence v3.0.

Identity and relationships

  • REPD reference

    5259

    Grove Solar Park (Phase 1) in REPD.

Output

Grid does not have this data yet. It will appear here once Elexon BMU metering is added.

Ownership and operator

  • Operator · REPD

    Solar Century

    REPD records 5259 as the operator.

  • Owner · REPD

    —

    The register records an operator, not an owner.

Related projects

  • Grove Solar Park (Phase 1)

    REPD · 5259 · Solar Century · South East · Hampshire

Change history

  • REPD Q2 2026

    3 Aug 2026 · REPD · 5.0 MW · Counted