Grid
Newry Biomass Phase 1 (Gas…: 2 MW Advanced conversion | Grid

Newry Biomass Phase 1 (Gasification)

Advanced conversionOperational

Grid ID ast_5aca23277d5345db

View on map

What is Newry Biomass Phase 1 (Gasification), and what is its status?

Advanced conversion in Northern Ireland. Details below come from the sources listed for each field.

Capacity

2.0 MW

Capacity basis

Counted REPD megawatts

Location precision

Published, approximate

Location

Published, approximate
100 km

54.21751, -6.33667

Open in Map

Contains public sector information licensed under the Open Government Licence v3.0.

Identity and relationships

  • REPD reference

    23

    Newry Biomass Phase 1 (Gasification) in REPD.

Output

Grid does not have this data yet. It will appear here once Elexon BMU metering is added.

Ownership and operator

  • Operator · REPD

    REACT Energy (Kedco)

    REPD records 23 as the operator.

  • Owner · REPD

    —

    The register records an operator, not an owner.

Related projects

  • Newry Biomass Phase 1 (Gasification)

    REPD · 23 · REACT Energy (Kedco) · Northern Ireland · Co. Down

Change history

  • REPD Q2 2026

    3 Aug 2026 · REPD · 2.0 MW · Counted

Source records