Crystal Rig Wind Farm Phase III: 13.8 MW Onshore wind | Grid

Crystal Rig Wind Farm Phase III

Onshore windOperational

Grid ID ast_71579393b0fad407

View on map

What is Crystal Rig Wind Farm Phase III, and what is its status?

Onshore wind in South and Central Scotland. Details below come from the sources listed for each field.

Capacity

13.8 MW

Capacity basis

Counted REPD megawatts

Location precision

Published, approximate

Location

Published, approximate
100 km

55.92641, -2.53448

Open in Map

Contains public sector information licensed under the Open Government Licence v3.0.

Contains public sector information licensed under the Open Government Licence v3.0.

Identity and relationships

  • REPD reference

    4215

    Crystal Rig Wind Farm Phase III in REPD.

  • DUKES site

    WON-000974

    Crystal Rig III in DUKES.

  • Same site

    name

    Same site in both registers, matched by name (high). REPD megawatts count. Distance 2722 m.

Output

Grid does not have this data yet. It will appear here once Elexon BMU metering is added.

Ownership and operator

  • Operator · REPD

    Fred Olsen Renewables

    REPD records 4215 as the operator.

  • Operator · DUKES

    Fred Olsen Renewables

    DUKES records WON-000974 as the operator.

  • Owner · DUKES, REPD

    —

    The register records an operator, not an owner.

Related projects

  • Crystal Rig Wind Farm Phase III

    REPD · 4215 · Fred Olsen Renewables · Scotland · Borders

  • Crystal Rig III

    DUKES · WON-000974 · Fred Olsen Renewables · Scotland

Change history

  • May 2026

    30 Jul 2026 · DUKES · 13.8 MW · Not counted

  • REPD Q2 2026

    3 Aug 2026 · REPD · 13.8 MW · Counted