Grid
Enviroparks Hirwaun Gener…: 20 MW Advanced conversion | Grid

Enviroparks Hirwaun Generation Site

Advanced conversionOperational

Grid ID ast_7300c4dc57068f3a

View on map

What is Enviroparks Hirwaun Generation Site, and what is its status?

Advanced conversion in South Wales. Details below come from the sources listed for each field.

Capacity

20.0 MW

Capacity basis

Counted REPD megawatts

Location precision

Published, approximate

Location

Published, approximate
100 km

51.75009, -3.53899

Open in Map

Contains public sector information licensed under the Open Government Licence v3.0.

Identity and relationships

  • REPD reference

    120

    Enviroparks Hirwaun Generation Site in REPD.

Output

Grid does not have this data yet. It will appear here once Elexon BMU metering is added.

Ownership and operator

  • Operator · REPD

    Enviroparks Operations

    REPD records 120 as the operator.

  • Owner · REPD

    —

    The register records an operator, not an owner.

Related projects

  • Enviroparks Hirwaun Generation Site

    REPD · 120 · Enviroparks Operations · Wales · Mid Glamorgan

Change history

  • REPD Q2 2026

    3 Aug 2026 · REPD · 20.0 MW · Counted