Capacity
66.0 MW
Grid ID ast_7cf11eb2217e2387
What is Moy Wind Farm (2nd Application), and what is its status?
Onshore wind in North Scotland. Details below come from the sources listed for each field.
66.0 MW
Counted REPD megawatts
Published, approximate
Contains public sector information licensed under the Open Government Licence v3.0.
Contains public sector information licensed under the Open Government Licence v3.0.
DUKES site
WON-000949
Moy in DUKES.
REPD reference
3647
Moy Wind Farm (2nd Application) in REPD.
Same site
coordinates
Same site in both registers, matched by coordinates (high). REPD megawatts count. Distance 307 m.
Operator · DUKES
Eneco Wind UK
DUKES records WON-000949 as the operator.
Operator · REPD
Eneco
REPD records 3647 as the operator.
Owner · DUKES, REPD
—
The register records an operator, not an owner.
Moy
DUKES · WON-000949 · Eneco Wind UK · Scotland
Moy Wind Farm (2nd Application)
REPD · 3647 · Eneco · Scotland · Highland
May 2026
30 Jul 2026 · DUKES · 66.0 MW · Not counted
REPD Q2 2026
3 Aug 2026 · REPD · 66.0 MW · Counted
DUKES
May 2026
REPD
REPD Q2 2026