Grid
Land At Actrees Farm: 5 MW Solar PV, West Midlands | Grid

Land At Actrees Farm

Solar PVOperational

Grid ID ast_8dba4d9666d4cb8d

View on map

What is Land At Actrees Farm, and what is its status?

Solar PV in West Midlands. Details below come from the sources listed for each field.

Capacity

5.0 MW

Capacity basis

Counted REPD megawatts

Location precision

Published, approximate

Location

Published, approximate
100 km

51.68153, -2.41943

Open in Map

Contains public sector information licensed under the Open Government Licence v3.0.

Identity and relationships

  • REPD reference

    5425

    Land At Actrees Farm in REPD.

Output

Grid does not have this data yet. It will appear here once Elexon BMU metering is added.

Ownership and operator

  • Operator · REPD

    Actrees Solar Power/ Vogt Solar

    REPD records 5425 as the operator.

  • Owner · REPD

    —

    The register records an operator, not an owner.

Related projects

  • Land At Actrees Farm

    REPD · 5425 · Actrees Solar Power/ Vogt Solar · South West · Gloucestershire

Change history

  • REPD Q2 2026

    3 Aug 2026 · REPD · 5.0 MW · Counted

Source records