Capacity
30.0 MW
Grid ID ast_e0ce9af5ec5dcb79
What is Rose And Crown Farm, and what is its status?
Solar PV in East England. Details below come from the sources listed for each field.
30.0 MW
Counted REPD megawatts
Published, approximate
Contains public sector information licensed under the Open Government Licence v3.0.
Contains public sector information licensed under the Open Government Licence v3.0.
DUKES site
SOL-001313
Rose & Crown in DUKES.
REPD reference
1783
Rose And Crown Farm in REPD.
Same site
coordinates
Same site in both registers, matched by coordinates (high). REPD megawatts count. Distance 833 m.
Operator · DUKES
Greencoat Capital
DUKES records SOL-001313 as the operator.
Operator · REPD
Elgin Energy EsCo
REPD records 1783 as the operator.
Owner · DUKES, REPD
—
The register records an operator, not an owner.
Rose & Crown
DUKES · SOL-001313 · Greencoat Capital · East of England
Rose And Crown Farm
REPD · 1783 · Elgin Energy EsCo · Eastern · Norfolk
May 2026
30 Jul 2026 · DUKES · 30.1 MW · Not counted
REPD Q2 2026
3 Aug 2026 · REPD · 30.0 MW · Counted
DUKES
May 2026
REPD
REPD Q2 2026