Capacity
20.0 MW
Grid ID ast_e77047f3f56aeb1b
What is Widnes 3MG Biomass/Mersey Bioenergy (CHP) Plant, and what is its status?
Biomass in North Wales, Merseyside and Cheshire. Details below come from the sources listed for each field.
20.0 MW
Counted REPD megawatts
Published, approximate
Contains public sector information licensed under the Open Government Licence v3.0.
REPD reference
190
Widnes 3MG Biomass/Mersey Bioenergy (CHP) Plant in REPD.
Operator · REPD
Burmeister & Wain Scandinavian (BWSC)/ Bioenergy Infrastructure Group
REPD records 190 as the operator.
Owner · REPD
—
The register records an operator, not an owner.
Widnes 3MG Biomass/Mersey Bioenergy (CHP) Plant
REPD · 190 · Burmeister & Wain Scandinavian (BWSC)/ Bioenergy Infrastructure Group · North West · Merseyside
REPD Q2 2026
3 Aug 2026 · REPD · 20.0 MW · Counted
REPD
REPD Q2 2026