Ardtornish Estate-Upgrade to existing: 1.5 MW Hydro | Grid

Ardtornish Estate-Upgrade to existing

HydroOperational

Grid ID ast_fbd3cb8636cf773e

View on map

What is Ardtornish Estate-Upgrade to existing, and what is its status?

Hydro in North Scotland. Details below come from the sources listed for each field.

Capacity

1.5 MW

Capacity basis

Counted REPD megawatts

Location precision

Published, approximate

Location

Published, approximate
100 km

56.55829, -5.68731

Open in Map

Contains public sector information licensed under the Open Government Licence v3.0.

Identity and relationships

  • REPD reference

    482

    Ardtornish Estate-Upgrade to existing in REPD.

Output

Grid does not have this data yet. It will appear here once Elexon BMU metering is added.

Ownership and operator

  • Operator · REPD

    Ardtornish Estate

    REPD records 482 as the operator.

  • Owner · REPD

    —

    The register records an operator, not an owner.

Related projects

  • Ardtornish Estate-Upgrade to existing

    REPD · 482 · Ardtornish Estate · Scotland · Highland

Change history

  • REPD Q2 2026

    3 Aug 2026 · REPD · 1.5 MW · Counted

Source records