Onshore wind · Scotland
Planning
- Planning
- Granted
- 23 Jul 2014
- DESNZ REPD, 3 Aug 2026
- Construction
- Built
- 20 Jul 2015
- DESNZ REPD, 3 Aug 2026
- Operational status
- Operational
- 15 Aug 2017
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Onshore wind project, epj_01769dba2159a6b9
Measures
- Rated power
- 172.8 MW
- Connection capacity
- Not published
- Storage energy
- Not published