Projects
Where is Brookfields Park, Brookfields Drive - Solar PV Panels up to?
Each status below comes from a named source and date.
Solar PV · England, Yorkshire and Humber
Planning
- Planning
- Granted
- 10 Jun 2024
- DESNZ REPD, 3 Aug 2026
- Construction
- Not started
- DESNZ REPD, 3 Aug 2026
- Operational status
- Proposed
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Solar PV project, epj_068212503aab5f3f
Measures
- Rated power
- 1.1 MW
- Connection capacity
- Not published
- Storage energy
- Not published