Projects
Where is The North West & South East Sides Of The A19 - Energy Storage Facility up to?
Each status below comes from a named source and date.
Battery · England, North East
Planning
- Planning
- Granted
- 25 Nov 2025
- DESNZ REPD, 3 Aug 2026
- Construction
- Not started
- DESNZ REPD, 3 Aug 2026
- Operational status
- Proposed
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Battery project, epj_06b2e14ead3d4be3
Measures
- Rated power
- 0.2 MW
- Connection capacity
- Not published
- Storage energy
- Not published