Projects
Where is Charlie Bighams, Mcnicol Drive - Solar Panels up to?
Each status below comes from a named source and date.
Solar PV · England, London
Planning
- Planning
- Granted
- 1 Feb 2024
- DESNZ REPD, 3 Aug 2026
- Construction
- Not started
- DESNZ REPD, 3 Aug 2026
- Operational status
- Proposed
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Solar PV project, epj_076f9a63e5b7a127
Measures
- Rated power
- 0.3 MW
- Connection capacity
- Not published
- Storage energy
- Not published