Projects
Where is Templeborough Biomass Power Plant- Rotherham up to?
Each status below comes from a named source and date.
Biomass · England, Yorkshire and Humber
Planning
- Planning
- Granted
- 9 Nov 2010
- DESNZ REPD, 3 Aug 2026
- Construction
- Built
- 26 Nov 2015
- DESNZ REPD, 3 Aug 2026
- Operational status
- Operational
- 28 Feb 2019
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Biomass project, epj_081e4345f11ff803
Measures
- Rated power
- 42.0 MW
- Connection capacity
- Not published
- Storage energy
- Not published