Where is Blackhillock Electricity Substation - Battery Energy Storage System up to?
Each status below comes from a named source and date.
Battery · Scotland
Planning
- Planning
- Granted
- 28 Feb 2022
- DESNZ REPD, 3 Aug 2026
- Construction
- Under construction
- 1 Feb 2023
- DESNZ REPD, 3 Aug 2026
- Operational status
- Proposed
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Battery project, epj_094f53572e044ce1
Measures
- Rated power
- 300.0 MW
- Connection capacity
- Not published
- Storage energy
- Not published