Grid

Projects

Projects

Where is Widnes 3MG Biomass/Mersey Bioenergy (CHP) Plant up to?

Each status below comes from a named source and date.

Biomass · England, North West

Planning

Planning
Granted
4 Apr 2013
DESNZ REPD, 3 Aug 2026
Construction
Built
1 Feb 2015
DESNZ REPD, 3 Aug 2026
Operational status
Operational
6 Feb 2017
DESNZ REPD, 3 Aug 2026

Connection

Connection
Biomass project, epj_0af3ff6aa91e6819

Measures

Rated power
20.0 MW
Connection capacity
Not published
Storage energy
Not published