Projects
Where is Quotient Sciences, Taylor Drive - Solar PV Panel Array up to?
Each status below comes from a named source and date.
Solar PV · England, North East
Planning
- Planning
- Granted
- 9 Nov 2023
- DESNZ REPD, 3 Aug 2026
- Construction
- Not started
- DESNZ REPD, 3 Aug 2026
- Operational status
- Proposed
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Solar PV project, epj_0ce716c6078f992d
Measures
- Rated power
- 4.0 MW
- Connection capacity
- Not published
- Storage energy
- Not published