Solar PV · England, Eastern

Planning

Planning
Granted
17 Oct 2024
DESNZ REPD, 3 Aug 2026
Construction
Not started
DESNZ REPD, 3 Aug 2026
Operational status
Proposed
DESNZ REPD, 3 Aug 2026

Connection

Connection
Solar PV project, epj_0f93c33170598cde

Measures

Rated power
0.3 MW
Connection capacity
Not published
Storage energy
Not published