Grid

Projects

Projects

Where is Wauntysswg Farm, near Tredagar up to?

Each status below comes from a named source and date.

Solar PV · Wales

Planning

Planning
Granted
1 Aug 2019
DESNZ REPD, 3 Aug 2026
Construction
Not started
DESNZ REPD, 3 Aug 2026
Operational status
Proposed
DESNZ REPD, 3 Aug 2026

Connection

Connection
Solar PV project, epj_10e4d9dab25b252d

Measures

Rated power
30.0 MW
Connection capacity
Not published
Storage energy
Not published