Where is Jack's Lane Wind Farm up to?
Each status below comes from a named source and date.
Onshore wind · England, Eastern
Planning
- Planning
- Granted
- 24 May 2012
- DESNZ REPD, 3 Aug 2026
- Construction
- Built
- 31 Jul 2014
- DESNZ REPD, 3 Aug 2026
- Operational status
- Operational
- 1 Apr 2015
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Onshore wind project, epj_112230db6b1ac9ab
Measures
- Rated power
- 13.8 MW
- Connection capacity
- Not published
- Storage energy
- Not published