Projects
Where is Bedhampton Pumping Station, Meyrick Road - Battery Energy Storage up to?
Each status below comes from a named source and date.
Battery · England, South East
Planning
- Planning
- Application submitted
- 1 May 2025
- DESNZ REPD, 3 Aug 2026
- Operational status
- Proposed
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Battery project, epj_1150bf62d0a4d497
Measures
- Rated power
- 150.0 MW
- Connection capacity
- Not published
- Storage energy
- Not published