Grid

Projects

Projects

Where is Bedhampton Pumping Station, Meyrick Road - Battery Energy Storage up to?

Each status below comes from a named source and date.

Battery · England, South East

Planning

Planning
Application submitted
1 May 2025
DESNZ REPD, 3 Aug 2026
Operational status
Proposed
DESNZ REPD, 3 Aug 2026

Connection

Connection
Battery project, epj_1150bf62d0a4d497

Measures

Rated power
150.0 MW
Connection capacity
Not published
Storage energy
Not published