Where is Poplars Anaerobic Digestion Facility (Waste AD) up to?
Each status below comes from a named source and date.
Anaerobic digestion · England, West Midlands
Planning
- Planning
- Granted
- 15 Jan 2010
- DESNZ REPD, 3 Aug 2026
- Construction
- Built
- 1 Jun 2011
- DESNZ REPD, 3 Aug 2026
- Operational status
- Operational
- 31 Jul 2011
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Anaerobic digestion project, epj_1236e27d57f2c3d2
Measures
- Rated power
- 6.0 MW
- Connection capacity
- Not published
- Storage energy
- Not published