Offshore wind · England, Offshore
Planning
- Planning
- Granted
- 12 Jan 2022
- DESNZ REPD, 3 Aug 2026
- Construction
- Not started
- DESNZ REPD, 3 Aug 2026
- Operational status
- Proposed
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Offshore wind project, epj_125f3a89f152a6ce
Measures
- Rated power
- 32.0 MW
- Connection capacity
- Not published
- Storage energy
- Not published