Projects
Where is Weeton Barracks, Grantham Road - Solar Panels up to?
Each status below comes from a named source and date.
Solar PV · England, North West
Planning
- Planning
- Granted
- 6 Sep 2024
- DESNZ REPD, 3 Aug 2026
- Construction
- Under construction
- 1 Feb 2025
- DESNZ REPD, 3 Aug 2026
- Operational status
- Proposed
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Solar PV project, epj_1349c29f90d580eb
Measures
- Rated power
- 0.7 MW
- Connection capacity
- Not published
- Storage energy
- Not published