Projects
Where is Brook Hall Farm up to?
Each status below comes from a named source and date.
Solar PV · England, South West
Planning
- Planning
- Revised
- 9 Feb 2015
- DESNZ REPD, 3 Aug 2026
- Operational status
- Proposed
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Solar PV project, epj_13bbe37358521c0a
Measures
- Rated power
- 10.0 MW
- Connection capacity
- Not published
- Storage energy
- Not published