Projects
Where is Masons Landfill, Bramford Road, Great Blakenham - Solar Farm up to?
Each status below comes from a named source and date.
Solar PV · England, Eastern
Planning
- Planning
- Granted
- 19 Mar 2024
- DESNZ REPD, 3 Aug 2026
- Construction
- Not started
- DESNZ REPD, 3 Aug 2026
- Operational status
- Proposed
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Solar PV project, epj_13db85aa7bf4a656
Measures
- Rated power
- 6.1 MW
- Connection capacity
- Not published
- Storage energy
- Not published