Solar PV · England, East Midlands

Planning

Planning
Permission expired
18 Mar 2019
DESNZ REPD, 3 Aug 2026

Connection

Connection
Solar PV project, epj_1445bc75546bcbef

Measures

Rated power
36.7 MW
Connection capacity
Not published
Storage energy
Not published