Projects
Where is Mill Of Peattie Farm, Kinnochtry Coupar - Battery Storage up to?
Each status below comes from a named source and date.
Battery · Scotland
Planning
- Planning
- Refused
- 9 Jul 2025
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Battery project, epj_1517729c6bc52975
Measures
- Rated power
- 18.0 MW
- Connection capacity
- Not published
- Storage energy
- Not published