Onshore wind · Scotland
Planning
- Planning
- Granted
- 16 Oct 2009
- DESNZ REPD, 3 Aug 2026
- Construction
- Built
- DESNZ REPD, 3 Aug 2026
- Operational status
- Operational
- 1 Dec 2009
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Onshore wind project, epj_16125e4a8d9e38e6
Measures
- Rated power
- 2.3 MW
- Connection capacity
- Not published
- Storage energy
- Not published