Anaerobic digestion · England, London
Planning
- Planning
- Granted
- 11 Nov 2013
- DESNZ REPD, 3 Aug 2026
- Construction
- Built
- 1 Apr 2016
- DESNZ REPD, 3 Aug 2026
- Operational status
- Operational
- 7 Jul 2017
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Anaerobic digestion project, epj_16b8fa3a02be63ea
Measures
- Rated power
- 1.4 MW
- Connection capacity
- Not published
- Storage energy
- Not published