Where is Skelton Grange Landfill Site, Pontefract Lane - Solar Farm up to?
Each status below comes from a named source and date.
Solar PV · England, Yorkshire and Humber
Planning
- Planning
- Granted
- 29 Sep 2023
- DESNZ REPD, 3 Aug 2026
- Construction
- Not started
- DESNZ REPD, 3 Aug 2026
- Operational status
- Proposed
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Solar PV project, epj_17d29a4071f16479
Measures
- Rated power
- 4.4 MW
- Connection capacity
- Not published
- Storage energy
- Not published