Where is Camilla Battery Storage up to?

Each status below comes from a named source and date.

Battery · Scotland

Planning

Planning
Granted
22 Oct 2022
DESNZ REPD, 3 Aug 2026
Construction
Built
1 Oct 2023
DESNZ REPD, 3 Aug 2026
Operational status
Operational
20 Mar 2024
DESNZ REPD, 3 Aug 2026

Connection

Connection
Battery project, epj_19604105bd362b85

Measures

Rated power
50.0 MW
Connection capacity
Not published
Storage energy
Not published