Projects
Where is Heck Food, Lime Lane - Solar Panels up to?
Each status below comes from a named source and date.
Solar PV · England, Yorkshire and Humber
Planning
- Planning
- Granted
- 8 Dec 2023
- DESNZ REPD, 3 Aug 2026
- Construction
- Built
- DESNZ REPD, 3 Aug 2026
- Operational status
- Operational
- 7 Jun 2024
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Solar PV project, epj_1c3bef9cadba3da9
Measures
- Rated power
- 0.2 MW
- Connection capacity
- Not published
- Storage energy
- Not published