Where is ICI No2 (Teesport) Landfill up to?
Each status below comes from a named source and date.
Landfill gas · England, North East
Planning
- Planning
- Granted
- 24 Sep 2021
- DESNZ REPD, 3 Aug 2026
- Construction
- Built
- DESNZ REPD, 3 Aug 2026
- Operational status
- Operational
- 1 Sep 2021
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Landfill gas project, epj_1c6a44970074ec0f
Measures
- Rated power
- 1.0 MW
- Connection capacity
- Not published
- Storage energy
- Not published