Where is Brassington Works, Manystones Lane - Solar Farm up to?
Each status below comes from a named source and date.
Solar PV · England, East Midlands
Planning
- Planning
- Granted
- 17 Oct 2024
- DESNZ REPD, 3 Aug 2026
- Construction
- Not started
- DESNZ REPD, 3 Aug 2026
- Operational status
- Proposed
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Solar PV project, epj_1d1a27e290b3a712
Measures
- Rated power
- 4.3 MW
- Connection capacity
- Not published
- Storage energy
- Not published