Where is Hayle Wave Hub (Test Site) up to?
Each status below comes from a named source and date.
Wave · England, Offshore
Planning
- Planning
- Granted
- 15 Jul 2009
- DESNZ REPD, 3 Aug 2026
- Construction
- Built
- 1 Jun 2010
- DESNZ REPD, 3 Aug 2026
- Operational status
- Operational
- 1 Sep 2010
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Wave project, epj_1d98ac548f63ebbf
Measures
- Rated power
- 23.0 MW
- Connection capacity
- Not published
- Storage energy
- Not published