Where is Milton of Fisherie Wind Cluster up to?

Each status below comes from a named source and date.

Onshore wind · Scotland

Planning

Planning
Granted
2 Nov 2012
DESNZ REPD, 3 Aug 2026
Construction
Built
1 Apr 2015
DESNZ REPD, 3 Aug 2026
Operational status
Operational
1 Feb 2016
DESNZ REPD, 3 Aug 2026

Connection

Connection
Onshore wind project, epj_1da55a8877b51829

Measures

Rated power
4.6 MW
Connection capacity
Not published
Storage energy
Not published