Projects
Where is Tiers Cross Solar Farm up to?
Each status below comes from a named source and date.
Solar PV · Wales
Planning
- Planning
- Granted
- 14 Oct 2013
- DESNZ REPD, 3 Aug 2026
- Construction
- Built
- 19 Dec 2013
- DESNZ REPD, 3 Aug 2026
- Operational status
- Operational
- 25 Oct 2014
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Solar PV project, epj_1dbdfbb50d8cfe85
Measures
- Rated power
- 24.0 MW
- Connection capacity
- Not published
- Storage energy
- Not published