Where is Land At Court Farm up to?

Each status below comes from a named source and date.

Solar PV · Wales

Planning

Planning
Granted
5 Jun 2015
DESNZ REPD, 3 Aug 2026
Construction
Built
15 Nov 2015
DESNZ REPD, 3 Aug 2026
Operational status
Operational
16 Mar 2016
DESNZ REPD, 3 Aug 2026

Connection

Connection
Solar PV project, epj_1de162896a6b792a

Measures

Rated power
2.2 MW
Connection capacity
Not published
Storage energy
Not published