Onshore wind · Wales
Planning
- Planning
- Granted
- 27 Aug 2013
- DESNZ REPD, 3 Aug 2026
- Construction
- Built
- 27 May 2016
- DESNZ REPD, 3 Aug 2026
- Operational status
- Operational
- 14 Sep 2017
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Onshore wind project, epj_1e7837406e35e90f
Measures
- Rated power
- 24.0 MW
- Connection capacity
- Not published
- Storage energy
- Not published