Onshore wind · Scotland
Planning
- Planning
- Granted
- 10 Mar 2021
- DESNZ REPD, 3 Aug 2026
- Construction
- Not started
- DESNZ REPD, 3 Aug 2026
- Operational status
- Proposed
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Onshore wind project, epj_20484cf232f9f350
Measures
- Rated power
- 38.4 MW
- Connection capacity
- Not published
- Storage energy
- Not published