Battery · England, West Midlands
Planning
- Planning
- Granted
- DESNZ REPD, 3 Aug 2026
- Construction
- Built
- 1 Jan 2019
- DESNZ REPD, 3 Aug 2026
- Operational status
- Operational
- 1 Jan 2020
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Battery project, epj_239be583f991b038
Measures
- Rated power
- 20.0 MW
- Connection capacity
- Not published
- Storage energy
- Not published