Battery · England, West Midlands

Planning

Planning
Granted
DESNZ REPD, 3 Aug 2026
Construction
Built
1 Jan 2019
DESNZ REPD, 3 Aug 2026
Operational status
Operational
1 Jan 2020
DESNZ REPD, 3 Aug 2026

Connection

Connection
Battery project, epj_239be583f991b038

Measures

Rated power
20.0 MW
Connection capacity
Not published
Storage energy
Not published