Grid

Projects

Projects

Where is Cwm Ivor Penyrheol Solar Farm up to?

Each status below comes from a named source and date.

Solar PV · Wales

Planning

Planning
Granted
23 May 2024
DESNZ REPD, 3 Aug 2026
Construction
Not started
DESNZ REPD, 3 Aug 2026
Operational status
Proposed
DESNZ REPD, 3 Aug 2026

Connection

Connection
Solar PV project, epj_23e6d5826ff901e2

Measures

Rated power
20.0 MW
Connection capacity
Not published
Storage energy
Not published