Battery · England, Eastern
Planning
- Planning
- Granted
- DESNZ REPD, 3 Aug 2026
- Construction
- Built
- 15 May 2014
- DESNZ REPD, 3 Aug 2026
- Operational status
- Closed
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Battery project, epj_24a61930ba81d06e
Measures
- Rated power
- 6.0 MW
- Connection capacity
- Not published
- Storage energy
- Not published