Where is Majors Hill/Turners Hill Solar Farm up to?
Each status below comes from a named source and date.
Solar PV · England, South East
Planning
- Planning
- Granted
- 2 Oct 2015
- DESNZ REPD, 3 Aug 2026
- Construction
- Built
- 8 Jan 2016
- DESNZ REPD, 3 Aug 2026
- Operational status
- Operational
- 15 Mar 2016
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Solar PV project, epj_27000432a1bbc48c
Measures
- Rated power
- 1.1 MW
- Connection capacity
- Not published
- Storage energy
- Not published