Projects
Where is Buslingthorpe Power Station (Leeds North) up to?
Each status below comes from a named source and date.
Biomass · England, Yorkshire and Humber
Planning
- Planning
- Granted
- 30 Dec 2010
- DESNZ REPD, 3 Aug 2026
- Construction
- Built
- DESNZ REPD, 3 Aug 2026
- Operational status
- Operational
- 14 Oct 2011
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Biomass project, epj_27079b903be844ed
Measures
- Rated power
- 2.0 MW
- Connection capacity
- Not published
- Storage energy
- Not published