Biomass · England, North West
Planning
- Planning
- Granted
- 30 Dec 2008
- DESNZ REPD, 3 Aug 2026
- Construction
- Built
- DESNZ REPD, 3 Aug 2026
- Operational status
- Operational
- 16 Mar 2012
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Biomass project, epj_274c998bb0f27f18
Measures
- Rated power
- 41.6 MW
- Connection capacity
- Not published
- Storage energy
- Not published