Where is Worset Lane - Solar Farm up to?

Each status below comes from a named source and date.

Solar PV · England, North East

Planning

Planning
Granted
26 Aug 2021
DESNZ REPD, 3 Aug 2026
Construction
Not started
DESNZ REPD, 3 Aug 2026
Operational status
Proposed
DESNZ REPD, 3 Aug 2026

Connection

Connection
Gate 2, Agreement held
31 May 2029
NESO TEC register, 13 Oct 2026

Measures

Rated power
50.0 MW
Connection capacity
200.0 MW
Storage energy
Not published